To prevent farmers from failing to irrigate irrigation, the government has set up a revival program for ex-Malguzari ponds. In the year 17-18, 379 were to evacuate from the tank. The entire sludge has been removed from the 9 4 tank and the construction of pond sludge in 120 tanks is still in progress.

Gondia Today News Network

Gondia: The Government has set up a revival program for the ex-harvesting ponds so that the farmers of non-irrigated crops should not face any problem. In the year 17-18, 379 were to evacuate from the tank. The entire sludge has been removed from the 9 4 tank and the construction of pond sludge in 120 tanks is still in progress. By 31 January, 3 lakh 9 thousand 706 cubic meters of sludge has been removed.
The sludge has been completely removed from Gondia taluka and work on the removal of sludge in 21 tank has started. A total of 68 thousand 547 cubic meter sludge was removed in this taluka. The sludge has been completely removed from Goregaon taluka and work on the removal of sludge in 18 ponds has started. 76 thousand 510 cubic meter sludge has been removed in this taluka. 17 sludge drains in Tiroda taluka have been completely removed and work on the removal of sludge in 18 ponds has started. In this taluka, 28 thousand 464 cubic meters of sludge has been removed. The mud of 10 tank in Amgaon taluka has been completely removed and work on 11 ponds has been started. 19 thousand 557 cubic meter sludge has been removed in this taluka.

Drain of 15 tank in Deori taluka has been completely removed and work on the removal of sludge in 15 tank has started. 19 thousand 11 cubic meters of sludge has been removed in this taluka. The sludge has been completely removed from the 12 tank in the road-Arjuni taluka and work on the removal of sludge in 13 tank has started. In this taluka, 58 thousand 149 cubic meters of sludge has been removed. The sludge drainage in Saalaksa taluka has been completely removed and work on the removal of sludge in 10 tank has started. In this taluka, 11,919 cubic meters of sludge has been removed.

The sludge in a basement of Arjuni-Morgaon taluka was not completely removed. Work on removal of sludge is going on. In this taluka, 27 thousand 549 cubic meters of sludge has been removed. In this way, 9 4 tank sludge has been completely removed and work on the removal of sludge in 120 tank has started. 3 lakh 9 706 cubic meters of sludge has been removed in this district.

387 ponds are rich in farmers

To overcome the water scarcity, the government started the revival program of the former Malgujari Talas through short-flowing irrigation department. In the year 2016-17, the lakes have been prepared to provide the farmers’ crops to the farmers by removing 8 lakh 11 thousand 30 meter of mud in 387 lakes.